No Comments

Wynwood OKs Unique Public-Private Deal To Bring An Apartment Building Devoted To Affordable Rental Units

A unique public-private partnership has assembled and will bring an apartment building to Wynwood’s southeastern corner devoted entirely to affordable rental units, atop ground floor retail.

Wynwood Works is proposed by Wynwood Works LLC, an affiliate of Magellan Housing, the developer selected by the Omni Community Redevelopment Agency (CRA) to redevelop the property at 2035, 2037 and 2043 N Miami Ave.

The project was approved Monday by the Wynwood Design Review Committee with conditions on a 3-to-2 vote.
The site is in the Wynwood Neighborhood Revitalization District (NRD-1), and within the CRA’s boundary.

Wynwood Works is designed as a 12-story multi-family residential attainable housing project, including 120 units ranging from studios to two bedrooms.

The development will total 179,105 square feet of floor space, and offer 5,698 square feet of ground floor commercial space on North Miami Avenue, with five levels of on-site enclosed parking for about 108 vehicles, and a mix of amenity spaces to support the residents.

Project attorney Steven J. Wernick said the project is participating in the Wynwood Attainable Mixed Income Program, recently established within the NRD-1, with 20% of the units to go to households at or below 50% Area Median Income (AMI), including 10% to Extremely Low Income (ELI) households (at or below 30% AMI).

Mr. Wernick said the project has been submitted and reviewed by the City of Miami Planning Department and Office of Zoning.

Wynwood Works is a key project for the Omni CRA and Wynwood NRD, areas experiencing revitalization and in need of housing for those of modest income increasingly being priced out of Miami’s urban neighborhoods, Mr. Wernick wrote to the city.

The lot is irregular shaped with 25,628 square feet, with a single thoroughfare frontage on North Miami Avenue. With required right-of-way dedications, the net lot area is 17,946 square feet.

Mr. Wernick wrote, “The property has a unique lot configuration, shaped by its location in proximity to the FEC Rail Line, which forms the rear yard of the property running southwest towards the intersection of North Miami Avenue and NE 20th Street.”

He said Omni CRA acquired the property, former site of the Lowenstein galleries, in 2018 to redevelop it with the CRA’s objectives.

The property has two small warehouses, which have been unoccupied for several years, and an overgrown gated parking lot. To the north is a parking lot and FPL transformer lines. To the west is North Miami Avenue, and a part of Wynwood that has remained industrial and seen little redevelopment since the NRD-1 was adopted in 2015.

The 120-unit housing program includes 48 studios (445-plus square feet), 66 one-bedroom apartments and six two-bedroom apartments. The residential component starts on the sixth story, accompanied by a gym, business center and community room.

Mr. Wernick wrote, “The project will be one of the first affordable housing new developments in Wynwood in many years, at a critical time when housing costs have continued to rise, making it increasingly challenging for retaining Miami’s workforce, artists, and others essential for the continued revitalization and growth of areas like Wynwood, Omni and Edgewater.”

Jennifer McConney-Gayoso, principal at Studio MC+G Architecture, detailed for the committee the specifics of the proposed façades and the materials to be used. She also explained areas where artwork will be installed, including unique shadow art on the south side of the building, and a catwalk on the second floor.

The site at one end is limited to about 50 feet.

“It was a difficult site to develop. We squeezed the envelope on this project,” she told the committee.

Even with the tight site, the plan shows 14% open space, more than the 10% zoning code requires.

Several committee members commended the developer and design team for bringing much needed affordable housing into Wynwood.

“It’s surprising you can actually do that in Wynwood,” one member said.

Some were critical of the building’s cake layered look, saying the components need more articulation and the art needs to come down into the ground floor level.

Committee member Erik Rutter said, “We do have to think more about the art, not just as a mural in a box. I like the shadow wall … Magellan is a great developer. This will be a great addition to the neighborhood.”

The committee’s motion to approve includes conditions: improve articulation and integration of the pedestal to the rest of the tower or accentuate/contrast against the rest of the tower; increase art treatments at ground floor level and increase articulation; address the east façade with art intervention; and conceal rooftop equipment.

Mr. Wernick said the applicant is wholly owned by Magellan Housing, an affordable housing developer active in Texas and Florida.

Magellan is developing Wynwood Works in partnership with the Omni CRA. In addition to owning the land, the CRA is providing financial support towards development costs.

 

Source:  Miami Today

No Comments

Pair Of Mixed-Use Towers Planned For Wynwood

On the eastern side of growing Wynwood a developer plans a large mixed-use residential project that will also bring in new commercial tenants.

PRH CHO Dragon Wynwood LLC plans to build the pair of neighboring buildings at 2804, 2810, 2819, 2828, 2838 and 2804 NW First Ave.

The city’s Urban Development Review Board considered the project at a virtual meeting and recommended it for approval with a couple of thoughts.

With a current working title of Wynwood 29, the vast development tops out at 375,383 square feet.

The project includes a 12-story building that connects to an 8-story portion, and a separate 8-story building across the street, with 248 multifamily residential units, 28,071 square feet of ground floor commercial uses, a garage for 372 vehicles and room to park 22 bicycles.

Wynwood 29 will include a pool and amenity deck. The garage is intended for both residential and commercial tenants, as well as patrons.

The project is to have 6,360 square feet of open space.

The collection of parcels is between Northwest 28th and 29th streets, split by Northwest First Avenue.

The 12-story portion is planned for the southwest corner of Northwest 29th Street and First Avenue. The southern end of that block has the connected 8 stories. The ground floor is set for retail uses.

What’s referred to in the plans as Parcel 2 is on the northeast corner of Northwest 28th Street and First Avenue. Planned there is the 8-story building, which has eight levels of parking, seven levels of residential and ground floor retail.

The property is currently vacant and is within both the T5-O and T6-8-O Zoning Transects and the Wynwood Neighborhood Revitalization District (NRD-1) Overlay.

Multifamily structures sit to the east and west of the property.

Attorney Brian Dombrowski, representing the developer, told the review board the project was previously approved in September 2016 and this is a slightly modified design, updated after the company gained an additional parcel.

In a letter to the city, Mr. Dombrowski detailed requests for one warrant and several waivers in order to construct Wynwood 29.

The developer is requesting a warrant to allow on-street maneuverability to access two loading berths. Turning movements associated with more than one loading berth per development may be permitted on-street by warrant, except along Wynwood Corridors, under Miami 21 zoning.

The project proposes on-street maneuverability to access two loading berths from Northwest 28th Street, on the western portion of the project, according to the letter.

The waivers being sought include:

  • Up to a 30% reduction in required parking within the quarter-mile radius of a Transit Corridor. The property is within a quarter mile of multiple bus and trolley stops.
  • Up to a 10% increase in lot size from 40,000 square feet to 44,000.
  • Up to 90% lot coverage through the Flexible Lot Coverage Program, of the NRD-1 Regulations. This additional lot coverage allows both the activation of the roof terrace as well enhancing the pedestrian realm.
  • Up to a 10% increase in lot coverage for the T6-8-O portion of the property, allowing 84.3% of coverage when 80% is allowed.
  • To allow vehicular entry, loading docks, and service entries from the primary frontage, Northwest 28th Street.
  • Up to a 10% reduction in the minimum square footage for a one-bedroom residential unit. Miami 21 typically requires a minimum square footage for a one-bedroom residential unit of 550 square feet. The project proposes one-bedroom units at 531 square feet, 3.5% below the minimum.

“By reducing the minimum one-bedroom unit size, the Project can provide more affordable units. The Project’s proximity to mass transit makes it a great candidate for smaller, more affordable units,” wrote Mr. Dombrowski.

 

“Urban Land Institute studies indicate that smaller units have stronger occupancy rates than typical apartments and individuals choosing to live in smaller units are attracted to them because of a desire to sacrifice space for lower per unit cost and proximity to transit, employment, and vibrant mixed-use neighborhoods,” he said.

The project is designed by the architectural firm of Arquitectonica. Ray Fort, of the firm, described details of the Wynwood 29 project during the virtual meeting.

Mr. Fort told the board: “This quadrant of Wynwood is becoming the residential sector of Wynwood … it is a little bit quieter – there aren’t as many bars – and surrounding projects are planned to be residential,”

Board Chair Willy Bermello said, “I think the project is beautifully designed.”

And while he complimented the bright colors proposed for the project, Mr. Bermello mentioned a concern with the longevity of painted stucco.

“The issue of our Florida sun is that it’s not forgiving when it comes to bright colored paints. [How do you] maintain the crispness of those colors over time?” he asked.

Mr. Bermello asked if they had considered brick for the project.

Mr. Fort said they did not and referred to the size of the development.

Board member Anthony Tzamtzis also voiced concern about the painted surfaces.

“Did you consider glazed tiles? I think the painted stucco is degrading the concept you are trying to promote, which is the industrial [look],” said Mr. Tzamtzis. But he went on to congratulate Mr. Fort for “an extremely elegant presentation and thoughtful design.”

 

Board member Dean Lewis said the project is “well thought out, well detailed.”

He suggested a pedestrian bridge over Northwest First Avenue to connect the buildings.

Attorney Iris Escarra, also representing the developer, said they have discussed a pedestrian bridge but said it would require a separate approval from the city commission. She said such a bridge may be an option.

Board member Ignacio Permuy said: “I commend you on an exceptional job, starting from the massing to the architecture of the buildings … I truly appreciate the screening on the parking garage.”

Mr. Permuy said he understood the others’ comments about the bright painted stucco but added, “I don’t mind the color scheme that much. I understand comments … but this shows levels of playfulness, it shows you enjoyed designing this project.”

 

Board member Robert Behar said: “I like the whole project. You’ve done a great job.”

A motion to recommend approval of the project passed unanimously, with recommendations including the developer considering connecting the buildings, perhaps with a bridge, and to consider materials other than stucco.

 