The permit was applied for in May, with the full plans filed on June 27 and now in review.
The hard construction cost is estimated on the permit at $69,800,000. Beauchamp Construction is listed as the contractor.
The project was first reviewed by the Wynwood Design Review Committee in April 2022.
A total demolition permit to clear the site was applied for last July. Then in August, a utilities deal for water and sewer was signed.
Wynwood Urby is planned to include:
- 289 apartments
- 8,000 square feet of full service restaurant
- 9,200 square feet of retail
- 1,450 square feet of office
- 193 parking spaces
Urby is a joint venture between David Barry and Brookfield Properties.
Amsterdam’s Concrete is the design architect, with 5G Studio the architect of record.
Source: Next Miami